Plumbing estimate or quote: what you are agreeing to

Provisional sums and prime cost items

A provisional sum is a figure set aside in a quote for work that cannot yet be priced properly. The final charge is expected to differ once the work is known. A prime cost sum, often shortened to PC sum, is an allowance for goods or materials still to be selected, such as a basin or tiles.

These are industry labels. Their effect in your contract depends on the words used, so do not rely on the heading. Ask the business to write down how each allowance will be turned into a charge.

A worked example

The figures are illustrative, chosen to make the arithmetic easy.

Line Before VAT With VAT at 20%
Allowance for floor repair £500 £600
Agreed actual cost £650 £780
Difference added to the bill £150 £180

Had the agreed cost been £350 before VAT, £150 plus £30 VAT would come off, provided the contract adjusts the allowance both ways. Check whether VAT applies to your trader and whether the allowance was shown with or without it.

Defined and undefined provisional sums

Formal building contracts may use the RICS New Rules of Measurement. As Designing Buildings explains, a defined provisional sum is described well enough for the contractor to allow for it in programme, planning and preliminaries (general site costs). The description should cover the nature of the work, how and where it is fixed, quantities showing its scope and any limitations. Without that, it is treated as undefined. A small domestic quote may not use these rules, so ask what yours means.

Provisional sum or prime cost sum

Provisional sum Prime cost sum
Common domestic use Undefined or uncertain work Items not yet chosen
Example Repairing floor timbers if found rotten Supply of a shower valve
What settles it Inspection, then a price you approve Your choice and its price
Main question Does it include labour and materials? Does it include fitting, delivery and markup?

Usage varies. Designing Buildings describes a prime cost sum more narrowly, as an allowance for work or materials from a subcontractor or supplier the client nominates. Follow the definition in your contract.

Which label should the line have?

What is unknown Better treatment
Whether the work is needed at all Provisional sum, spent only after inspection and approval
How much of a known task there is Unit rate, for example per board replaced
Which product you will choose Prime cost sum with the allowance stated
Nothing: task and product are settled Fixed price line, no allowance

Why a low allowance misleads

Two quotes can describe the same bathroom while allowing different amounts for the same unknowns. The one with smaller allowances looks cheaper and may not be. When comparing, list every allowance separately, then compare the fixed part and the uncertain part side by side. Where goods are involved, ask each business to use the same allowance or name the same product. A bathroom quote split by trade makes those lines easier to find.

Two quotes, same job

Illustrative figures including VAT:

Line Quote A Quote B
Fixed work £4,000 £4,500
Floor repair allowance £200 £600
Headline total £4,200 £5,100
Total if floor repair costs £600 under both £4,600 £5,100

This assumes each contract adjusts the allowance to the actual cost. A £900 gap on the front page becomes £500.

Six things to get in writing

  1. What exactly the sum covers and why it cannot be fixed now.
  2. Whether VAT is included.
  3. Whether labour, delivery, waste and the trader's overhead are inside it or added.
  4. How the actual cost will be evidenced, for instance a supplier invoice or timed record.
  5. That unspent money comes off the total.
  6. That nothing above the figure is spent without your written approval.

Sample wording to propose:

Allowance of £[amount] including VAT for [item]. Final charge to be [method]. Any saving to be credited. No expenditure above this figure without the customer's written agreement before the work or order.

This is a drafting suggestion, not a standard clause. Change it to fit your job.

Where a trader gives pricing to a consumer and the total cannot reasonably be worked out in advance, consumer contract rules for off-premises and distance sales require the manner of calculating it to be stated. A payment on top of the price agreed for the main obligation needs express consent before you are bound. Whether an overspent allowance counts as such an extra depends on what your documents say, which is a good reason to settle it beforehand.

If a contract does not fix a price or the method for a service at all, you pay a reasonable price and no more.

Turning an allowance into a fixed price

Often the unknown can be removed before work begins. Choose the goods and give their model numbers. Pay for an opening-up visit so that the floor, wall or pipe can be seen. Ask the business to quote the likely remedy as a separate optional line, with a unit rate if the quantity is unknown, such as a price per board replaced.

Set a date by which you will make each choice. A late decision can delay ordering and push the programme out.

At the end of the job

Ask for a short reconciliation: each allowance, the actual amount, the evidence, and the difference. Check it against your written approvals before paying the final invoice. Add any unresolved line to your records and query it in writing.

For the wider description of the job, use the scope of works template.

For your own job, ask for a free written quote and request that every allowance is shown on its own line.

Questions people ask

Do I pay the full provisional sum if it is not used?

It depends on the contract. A common clause removes the sum and substitutes the value of the work actually done, so get that written into your agreement.

Can the final cost exceed the provisional sum?

Yes, the figure is an allowance and the adjusted price can be higher or lower. Agree in writing that no spending above it happens without your approval.

What does provisional sum mean in a quote?

A figure set aside for work that cannot yet be priced properly. The final charge is expected to change once the work is known.

What is the difference between a provisional sum and a PC sum?

A provisional sum usually covers uncertain work. A prime cost sum usually covers goods or supplier work still to be selected. Your contract's definition decides.