A plumbing estimate is a rough guess, so the final bill may be higher. A quote is a fixed price for described work. Citizens Advice draws that line, and says an accepted quote is binding whether or not it is written down. Read the wording as well as the heading, and ask which figure is fixed.
Quote and estimate compared
| Question | Quote | Estimate |
|---|---|---|
| What is the figure? | A fixed price | A rough guess |
| What should be in writing? | Work, materials, VAT, validity and when the price may change | The assumptions and what would move the figure |
| Before accepting | Check the scope and exclusions | Ask for a fixed figure or a spending limit |
If no price or method of working it out was fixed, section 51 of the Consumer Rights Act 2015 means a consumer pays a reasonable price and no more.
When a quoted price can change
Citizens Advice says a trader generally cannot charge more than the quote unless you ask for extra work, you agree to pay for extra work they say is needed, or the original figure was a genuine mistake. See is a quote legally binding for the detail.
The paperwork, one piece at a time
Start with quotation vs invoice, then write a scope of works so that several businesses price the same job. Other guides cover provisional sums, how long a quote is valid, how many quotes to get and stage payments. To find gaps in a document you hold, use the quote checker.
Questions people ask
Is an estimate binding?
An accepted estimate can still form a contract, but its figure is not a fixed price. Ask for the assumptions behind it and agree a limit.
What should a written quote include?
Citizens Advice lists a fixed total, a breakdown of work and materials, how long the price is valid, whether VAT is included and when the price could change.